This project infills multiple gaps in sidewalk, replaces ADA non-compliant curb ramps, constructs new ADA curb ramps where missing, adds curb extensions at strategic locations to reduce crossing distance and reduce traffic speeds, re-stripes shoulders, adds signage and bike symbols to provide designated bike lanes, and extends the pedestrian transportation network on Linwood Avenue. Sidewalk infill gaps are located on Linwood Avenue, 6th Avenue, and 7th Avenue. The project also includes the addition of a marked crossing in the vicinity of a transit stop. Safety is improved by building sidewalk and ramps removing pedestrians from the roadway and improves safety for students walking to Michael T Simmons Elementary School, which has an active Walk and Roll program to reduce bus trips. Vehicular, bicyclist and pedestrian mobility will improve, while significantly enhancing safety for all transportation modes.
Projects — TIB Project Information
TIB Project Information
City of Tumwater's Linwood Avenue Sidewalk
P-W-196(P05)-1
P-W-196(P05)-1
Linwood Avenue Sidewalk
Susitna Ln to 2nd Ave
FY 2023 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $371,250
County: Thurston | Legislative District: 22 | Project Length: 0.44 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/13/2024
Project Information
Lead Agency | TUMWATER |
Funding Year | 2023 |
Program | SP |
Current Phase | Construction |
Legislative District | 22 |
Congressional District | 10 |
Federal Route Number | 5206 |
Project Length | 0.44 mi. |
ADT | 8,000 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Mary Heather Ames |
Contact Email | mhames@ci.tumwater.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/13/2024 |
Cultural Resource Assessment | IDP |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 06/24/2024 | |
Predesign Approval | ||
Design Approval | 04/30/2022 | 04/08/2022 |
Bid Auth. Approval | 06/30/2024 | 06/24/2024 |
Construction Approval | 07/30/2024 | 07/18/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 22,500 | 140,000 |
Right of Way | 0 | 0 |
Total Design | 22,500 | 140,000 |
Construction Engineering | 22,500 | 180,690 |
Construction Contract | 326,250 | 1,420,882 |
Other Construction | 0 | 0 |
Total Construction | 348,750 | 1,601,572 |
Total TIB Funding | 371,250 | 1,741,572 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TUMWATER | 1,370,322 | 78.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,370,322 | 78.7% |
Project Description
Sidewalk infill will occur within the project limits, substandard design and condition sidewalk segments will be reconstructed, and crossings will be improved throughout project limits including curb extensions and markings where warranted.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |