13th St connects residents to Penny Playground, Chehalis Sports Complex, and Shaw Aquatic Center. This route is a main connector from residential areas to WF West High School. The sidewalk on the southeast side of 13th St has intermittent gaps and the majority lacks curb ramps and marked crosswalks from Williams Ave up to Market Blvd. There is existing sidewalk on the northwest side of 13th St, but there is a long unprotected crossing from Williams Ave to Market Blvd, making the sidewalk on this side of the road inaccessible to residents on the southeast side of 13th St.
Projects — TIB Project Information
TIB Project Information
City of Chehalis's SW 13th Street Sidewalk
P-W-193(P01)-1
P-W-193(P01)-1
SW 13th Street Sidewalk
SW William Ave to S Market Blvd
FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $256,468
County: Lewis | Legislative District: 20 | Project Length: 730.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/14/2024
Project Information
Lead Agency | CHEHALIS |
Funding Year | 2025 |
Program | ATP |
Current Phase | Construction |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 5669 |
Project Length | 730.00 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Lance Bunker |
Contact Email | lbunker@ci.chehalis.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/14/2024 |
Cultural Resource Assessment | IDP |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | 06/07/2024 | |
Predesign Approval | ||
Design Approval | 02/29/2024 | 02/09/2024 |
Bid Auth. Approval | 05/03/2024 | 06/07/2024 |
Construction Approval | 06/30/2024 | 07/03/2024 |
Project Closeout | 09/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 31,050 | 34,500 |
Right of Way | 0 | 0 |
Total Design | 31,050 | 34,500 |
Construction Engineering | 31,050 | 31,260 |
Construction Contract | 207,000 | 219,205 |
Other Construction | 0 | 0 |
Total Construction | 238,050 | 250,465 |
Funding Surplus | - 12,632 | |
Total TIB Funding | 256,468 | 284,965 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHEHALIS | 28,497 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 28,497 | 10.0% |
Project Description
Replace noncompliant ADA ramps, construct ADA ramps where traffic curb barriers exist, infill sidewalk adjacent to existing curb, construct ADA compliant driveways at sidewalk infill areas, provide marked crossings on side streets, add an RRFB for the long crossing at the west leg of Williams Ave and 13th St.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |