Sumner Ave (US 101) in Aberdeen, WA is designated as a Pacific Coast Scenic Byway and is the primary route for tourists traveling west to the ocean beach cities including Ocean Shores and Seabrook. This is a pedestrian safety improvement project that completes gaps in the sidewalk facilities along Sumner Ave (US 101). The south side of Sumner Ave between Myrtle St and Williams St has significant gaps in the pedestrian facilities.
Projects — TIB Project Information
TIB Project Information
City of Aberdeen's Sumner Avenue (SR 101) Sidewalk
P-W-189(P03)-1
P-W-189(P03)-1
Sumner Avenue (SR 101) Sidewalk
Maple St to Williams St
FY 2024 Active Transportation Program
Current Phase : Design
Total TIB Funding : $450,000
County: Grays Harbor | Legislative District: 19 | Project Length: 4,000.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/09/2024
Project Information
Lead Agency | ABERDEEN |
Funding Year | 2024 |
Program | ATP |
Current Phase | Design |
Legislative District | 19 |
Congressional District | 6 |
Federal Route Number | 0101 |
Project Length | 4000.00 mi. |
ADT | 11,800 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Kyle Fisher |
Contact Email | kfisher@aberdeenwa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 02/09/2024 |
Cultural Resource Assessment | CRA & BER |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/12/2023 |
Bid Auth. Approval | 02/01/2025 | |
Construction Approval | 03/01/2025 | |
Project Closeout | 12/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 42,522 | 107,890 |
Right of Way | 0 | 0 |
Total Design | 42,522 | 107,890 |
Construction Engineering | 53,151 | 134,860 |
Construction Contract | 354,327 | 899,025 |
Other Construction | 0 | 0 |
Total Construction | 407,478 | 1,033,885 |
Total TIB Funding | 450,000 | 1,141,775 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ABERDEEN | 341,775 | 29.9% |
WSDOT Funding | 0 | 0.0% |
WSDOT Transportation Alternatives Program | 350,000 | 30.7% |
Total Local Funding | 691,775 | 60.6% |
Project Description
Construct sidewalk to eliminate gaps in the pedestrian corridor.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |