US 101 is the primary route between the City of Aberdeen and the City of Cosmopolis, but this section of the corridor has gaps in the existing sidewalk, has many non-ADA compliant curb ramps, and lacks bicycle facilities requiring bicyclists to travel in the lanes of US 101.
Projects — TIB Project Information
TIB Project Information
City of Aberdeen's US 101 Safety Improvements
P-W-189(P04)-1
P-W-189(P04)-1
US 101 Safety Improvements
US 101 from the City of Cosmopolis MP 81.73 to the Chehalis River Bridge MP 83.17
FY 2025 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $450,000
County: Grays Harbor | Legislative District: 19 | Project Length: 2,350.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | ABERDEEN | 
| Funding Year | 2025 | 
| Program | ATP | 
| Current Phase | Bid Authorization | 
| Legislative District | 19 | 
| Congressional District | 6 | 
| Federal Route Number | 0101 | 
| Project Length | 2350.00 mi. | 
| ADT | 9,400 | 
| Functional Class | Principal | 
| Type of Work | Pedestrian | 
| Project Contact | Kyle Fisher | 
| Contact Email | kfisher@aberdeenwa.gov | 
| TIB Engineer | Chris Langhoff | 
| Last Payment Date | |
| Cultural Resource Assessment | Not Required | 
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 01/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 12/20/2023 | 
| Bid Auth. Approval | 10/30/2025 | 10/21/2025 | 
| Construction Approval | 12/01/2025 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date | 
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 | 
| Design Study | 0 | 0 | 
| Total Predesign | 0 | 0 | 
| Special Study | 0 | 0 | 
| Design | 0 | 0 | 
| Right of Way | 0 | 0 | 
| Total Design | 0 | 0 | 
| Construction Engineering | 58,776 | 288,000 | 
| Construction Contract | 391,224 | 1,917,000 | 
| Other Construction | 0 | 0 | 
| Total Construction | 450,000 | 2,205,000 | 
| Total TIB Funding | 450,000 | 2,205,000 | 
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ABERDEEN | 508,231 | 23.0% | 
| WSDOT Funding | 0 | 0.0% | 
| STP | 1,246,769 | 56.5% | 
| Total Local Funding | 1,755,000 | 79.5% | 
Project Description
Preliminary studies have demonstrated that a 3-lane section will accommodate anticipated growth and that a road diet is warranted. The existing 4-lane section will be converted to a 3-lane section to provide dedicated bike lanes.
Existing Condition
Project Benefits
- Improves pedestrian safety;
 - Removes ADA barriers;
 - Builds multimodal facilities
 
Project Delays
| Delay Type | Resolution Date | Comments | 
|---|---|---|
No delayed project history.  | 
                                                    ||