A critical sidewalk link is absent along Evergreen Way, from 42nd to Schmid Ball Fields, posing safety risks for pedestrians. Nearby, Washougal School District, Jemtegaard Middle School, and Schmid Ball Fields amplify the urgency. This sidewalk connects to 39th Street, a vital route for many residential areas. Presently, schoolchildren walk by the roadside, lacking protection from traffic. Addressing this gap is essential for community safety and convenience.
Projects — TIB Project Information
TIB Project Information
City of Washougal's Evergreen Way Sidewalk
P-W-186(P05)-1
P-W-186(P05)-1
Evergreen Way Sidewalk
42nd St to Schmid Park
FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $392,345
County: Clark | Legislative District: 17 | Project Length: 800.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/14/2024
Project Information
Lead Agency | WASHOUGAL |
Funding Year | 2025 |
Program | ATP |
Current Phase | Construction |
Legislative District | 17 |
Congressional District | 3 |
Federal Route Number | 7040 |
Project Length | 800.00 mi. |
ADT | 4,925 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Scott Collins |
Contact Email | Scott.Collins@cityofwashougal.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/14/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | 04/01/2024 | |
Predesign Approval | ||
Design Approval | 01/01/2024 | 12/12/2023 |
Bid Auth. Approval | 05/01/2024 | 05/31/2024 |
Construction Approval | 06/21/2024 | 07/19/2024 |
Project Closeout | 10/15/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 95,200 | 45,909 |
Right of Way | 0 | 0 |
Total Design | 95,200 | 45,909 |
Construction Engineering | 10,200 | 39,043 |
Construction Contract | 418,364 | 376,630 |
Other Construction | 0 | 0 |
Total Construction | 428,564 | 415,673 |
Funding Surplus | - 131,419 | |
Total TIB Funding | 392,345 | 461,582 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WASHOUGAL | 69,237 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 69,237 | 15.0% |
Project Description
This project will establish a new sidewalk, connecting existing walkways and ensuring a pathway from the school district, Jemtegaard, and ballfields. In addition to enhancing accessibility, the project will encompass drainage improvements and the installation of ADA-compliant curb ramps.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |