City of Granite Falls's W Stanley Street Sidewalk

P-P-820(P05)-1

P-P-820(P05)-1
W Stanley Street Sidewalk

Jordan Rd to Prospect Ave

FY 2024 Active Transportation Program
Current Phase : Design
Total TIB Funding : $496,400

County: Snohomish   |   Legislative District: 39   |   Project Length: 960.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency GRANITE FALLS
Funding Year 2024
Program ATP
Current Phase Design
Legislative District 39
Congressional District 1
Federal Route Number 2752
Project Length 960.00 mi.
ADT 11,300
Functional Class Minor
Type of Work Pedestrian
Project Contact Brent Kirk
Contact Email brent.kirk@ci.granite-falls.wa.us
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/22/2022
Bid Auth. Approval 04/15/2024
Construction Approval 05/01/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 39,704 41,800
Right of Way 0 0
Total Design 39,704 41,800
     
Construction Engineering 59,557 62,700
Construction Contract 397,139 418,100
Other Construction 0 0
Total Construction 456,696 480,800
     
Total TIB Funding 496,400 522,600

Local Funding Partners

Funding Amount Percent
GRANITE FALLS 26,200 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 26,200 5.0%

Project Description

Install new cement concrete curb, gutter and sidewalks on the north side of Stanley Street to fill in the gaps in the existing sidewalk system.