Stanley Street is the main east-west corridor through the City. Previous projects, funded by both the City and Developers, have installed sidewalks on both sides of the street from Jordan Road to Alder Avenue with the exception of two gaps on the north side of Stanley Street. The gaps include Jordan Road to the west side of the O Reilly Auto Parts frontage improvements (approximately 500 feet) and from the east side of the O Reilly Auto Parts frontage improvements to east of the Napa Auto Parts store (approximately 460 feet). Closing these gaps will complete the pedestrian facilities through the core of the City.
Projects — TIB Project Information
TIB Project Information
City of Granite Falls's W Stanley Street Sidewalk
P-P-820(P05)-1
P-P-820(P05)-1
W Stanley Street Sidewalk
Jordan Rd to Prospect Ave
FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $570,860
County: Snohomish | Legislative District: 39 | Project Length: 960.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | GRANITE FALLS |
Funding Year | 2024 |
Program | ATP |
Current Phase | Construction |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 2752 |
Project Length | 960.00 mi. |
ADT | 11,300 |
Functional Class | Minor |
Type of Work | Pedestrian |
Project Contact | Brent Kirk |
Contact Email | brent.kirk@ci.granite-falls.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/22/2022 |
Bid Auth. Approval | 05/10/2024 | 05/13/2024 |
Construction Approval | 06/05/2024 | 06/14/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 39,704 | 52,140 |
Right of Way | 0 | 0 |
Total Design | 39,704 | 52,140 |
Construction Engineering | 59,557 | 46,760 |
Construction Contract | 397,139 | 661,730 |
Other Construction | 0 | 0 |
Total Construction | 456,696 | 708,490 |
Funding Increase | 74,460 | |
Total TIB Funding | 570,860 | 760,630 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRANITE FALLS | 189,770 | 24.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 189,770 | 24.9% |
Project Description
Install new cement concrete curb, gutter and sidewalks on the north side of Stanley Street to fill in the gaps in the existing sidewalk system.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |