Town of Eatonville's West Eatonville Sidewalk Improvements

P-P-811(P03)-1

P-P-811(P03)-1
West Eatonville Sidewalk Improvements

Multiple Locations

FY 2025 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $399,076

County: Pierce   |   Legislative District: 2   |   Project Length: 4,553.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 10/28/2024

Project Information

Lead Agency EATONVILLE
Funding Year 2025
Program ATP
Current Phase Bid Authorization
Legislative District 2
Congressional District 8
Federal Route Number 9999
Project Length 4553.00 mi.
ADT 500
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Eric Phillips
Contact Email townadmin@eatonville-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 10/28/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/10/2024
Bid Auth. Approval 11/15/2024 11/12/2024
Construction Approval 12/18/2024
Project Closeout 09/04/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 48,450 51,000
Right of Way 0 0
Total Design 48,450 51,000
     
Construction Engineering 32,300 34,000
Construction Contract 318,326 335,080
Other Construction 0 0
Total Construction 350,626 369,080
     
Total TIB Funding 399,076 420,080

Local Funding Partners

Funding Amount Percent
EATONVILLE 21,004 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 21,004 5.0%

Project Description

This project will replace old curb ramps with ADA-compliant curb ramps, replace cracked sidewalks and driveways. In addition, remove obstructions such as relocating a mailbox that is limiting the walkable width of the sidewalk, and remove trees and vegetation that are causing the surrounding infrastructure to be displaced or are causing obstructions.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.