The main pedestrian traffic routes between west Eatonville and the high, middle and grade schools and to the central business area, there are several obstructions and trip hazards that make it difficult for pedestrians to walk. Specifically, there are areas with cracked sidewalks, objects blocking walking paths and non-compliant ADA ramps.
Projects — TIB Project Information
TIB Project Information
Town of Eatonville's West Eatonville Sidewalk Improvements
P-P-811(P03)-1
P-P-811(P03)-1
West Eatonville Sidewalk Improvements
Multiple Locations
FY 2025 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $399,076
County: Pierce | Legislative District: 2 | Project Length: 4,553.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/28/2024
Project Information
Lead Agency | EATONVILLE |
Funding Year | 2025 |
Program | ATP |
Current Phase | Bid Authorization |
Legislative District | 2 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 4553.00 mi. |
ADT | 500 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Eric Phillips |
Contact Email | townadmin@eatonville-wa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 10/28/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2024 | 01/10/2024 |
Bid Auth. Approval | 11/15/2024 | 11/12/2024 |
Construction Approval | 12/18/2024 | |
Project Closeout | 09/04/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 48,450 | 51,000 |
Right of Way | 0 | 0 |
Total Design | 48,450 | 51,000 |
Construction Engineering | 32,300 | 34,000 |
Construction Contract | 318,326 | 335,080 |
Other Construction | 0 | 0 |
Total Construction | 350,626 | 369,080 |
Total TIB Funding | 399,076 | 420,080 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EATONVILLE | 21,004 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 21,004 | 5.0% |
Project Description
This project will replace old curb ramps with ADA-compliant curb ramps, replace cracked sidewalks and driveways. In addition, remove obstructions such as relocating a mailbox that is limiting the walkable width of the sidewalk, and remove trees and vegetation that are causing the surrounding infrastructure to be displaced or are causing obstructions.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |