Town of Eatonville's West Eatonville Sidewalk Improvements

P-P-811(P03)-1

P-P-811(P03)-1
West Eatonville Sidewalk Improvements

Multiple Locations

FY 2025 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $325,638

County: Pierce   |   Legislative District: 2   |   Project Length: 4,553.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/14/2025

Project Information

Lead Agency EATONVILLE
Funding Year 2025
Program ATP
Current Phase Audit
Legislative District 2
Congressional District 8
Federal Route Number 9999
Project Length 4553.00 mi.
ADT 500
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Eric Phillips
Contact Email townadmin@eatonville-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/14/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/10/2024
Bid Auth. Approval 11/15/2024 11/12/2024
Construction Approval 01/07/2025 01/03/2025
Project Closeout 09/04/2025 04/03/2025
Audit Date   04/14/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 48,450 57,492
Right of Way 0 0
Total Design 48,450 57,492
     
Construction Engineering 32,300 34,793
Construction Contract 318,326 250,492
Other Construction 0 0
Total Construction 350,626 285,285
     
Funding Increase 26,959  
Funding Surplus - 100,397  
Total TIB Funding 325,638 342,777

Local Funding Partners

Funding Amount Percent
EATONVILLE 17,139 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 17,139 5.0%

Project Description

This project will replace old curb ramps with ADA-compliant curb ramps, replace cracked sidewalks and driveways. In addition, remove obstructions such as relocating a mailbox that is limiting the walkable width of the sidewalk, and remove trees and vegetation that are causing the surrounding infrastructure to be displaced or are causing obstructions.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.