Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Buckley's Foothills Trail Crossing

P-P-808(P01)-1

P-P-808(P01)-1
Foothills Trail Crossing

Main St

FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $219,276

County: Pierce   |   Legislative District: 31   |   Project Length: 150.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 12/28/2023

Project Information

Lead Agency BUCKLEY
Funding Year 2024
Program ATP
Current Phase Construction
Legislative District 31
Congressional District 8
Federal Route Number 3358
Project Length 150.00 mi.
ADT 1,500
Functional Class Collector
Type of Work Safety
Project Contact Chris Banks
Contact Email cbanks@cityofbuckley.com
TIB Engineer Greg Armstrong
Last Payment Date 12/28/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/15/2022
Bid Auth. Approval 12/01/2023 11/29/2023
Construction Approval 02/14/2024 01/24/2024
Project Closeout 08/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,178 30,450
Right of Way 0 0
Total Design 25,178 30,450
     
Construction Engineering 25,164 31,454
Construction Contract 167,759 212,209
Other Construction 0 0
Total Construction 192,923 243,663
     
Funding Increase 1,175  
Total TIB Funding 219,276 274,113

Local Funding Partners

Funding Amount Percent
BUCKLEY 54,837 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 54,837 20.0%

Project Description

This project will construct a refuge island and curb bulbs which will narrow the crossing distance that trail users are exposed to vehicle traffic and traffic calming. Improved signage will enhance the visibility of the crossing.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments