There is a documented safety issue at the Foothills Trail crossing at Main Street. There has been two documented bicycle/ped -vs- vehicle accidents at this crossing since 2019. The marked crossing is mid-block on a skew. There are some sight distance issues for vehicles traveling northbound on SR-410 and talking a right-hand turn to head eastbound on Main.
Projects — TIB Project Information
TIB Project Information
City of Buckley's Foothills Trail Crossing
P-P-808(P01)-1
P-P-808(P01)-1
Foothills Trail Crossing
Main St
FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $219,276
County: Pierce | Legislative District: 31 | Project Length: 150.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/28/2023
Project Information
Lead Agency | BUCKLEY |
Funding Year | 2024 |
Program | ATP |
Current Phase | Construction |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 3358 |
Project Length | 150.00 mi. |
ADT | 1,500 |
Functional Class | Collector |
Type of Work | Safety |
Project Contact | Chris Banks |
Contact Email | cbanks@cityofbuckley.com |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/28/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/15/2022 |
Bid Auth. Approval | 12/01/2023 | 11/29/2023 |
Construction Approval | 02/14/2024 | 01/24/2024 |
Project Closeout | 08/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 25,178 | 30,450 |
Right of Way | 0 | 0 |
Total Design | 25,178 | 30,450 |
Construction Engineering | 25,164 | 31,454 |
Construction Contract | 167,759 | 212,209 |
Other Construction | 0 | 0 |
Total Construction | 192,923 | 243,663 |
Funding Increase | 1,175 | |
Total TIB Funding | 219,276 | 274,113 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BUCKLEY | 54,837 | 20.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 54,837 | 20.0% |
Project Description
This project will construct a refuge island and curb bulbs which will narrow the crossing distance that trail users are exposed to vehicle traffic and traffic calming. Improved signage will enhance the visibility of the crossing.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |