City of Snoqualmie's 384th Ave SE Sidewalk

P-P-806(P04)-1

P-P-806(P04)-1
384th Ave SE Sidewalk

Newton Ave to SE Kimball Creek Dr

FY 2024 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $526,198

County: King   |   Legislative District: 5   |   Project Length: 0.40   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 07/16/2025

Project Information

Lead Agency SNOQUALMIE
Funding Year 2024
Program ATP
Current Phase Audit
Legislative District 5
Congressional District 8
Federal Route Number 2820
Project Length 0.40 mi.
ADT 500
Functional Class Collector
Type of Work Pedestrian
Project Contact Patrick Fry
Contact Email pfry@snoqualmiewa.gov
TIB Engineer Greg Armstrong
Last Payment Date 07/16/2025
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date   02/20/2023
Predesign Approval
Design Approval 01/01/2023 12/13/2022
Bid Auth. Approval 04/01/2024 03/26/2024
Construction Approval 04/30/2024 05/02/2024
Project Closeout 07/31/2025 07/17/2025
Audit Date   07/16/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 64,349 581,968
Right of Way 0 0
Total Design 64,349 581,968
     
Construction Engineering 0 78,669
Construction Contract 484,507 2,964,699
Other Construction 0 128,597
Total Construction 484,507 3,171,965
     
Funding Increase 7,289  
Funding Surplus - 29,947  
Total TIB Funding 526,198 3,753,933

Local Funding Partners

Funding Amount Percent
SNOQUALMIE 3,227,735 86.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 3,227,735 86.0%

Project Description

A sidewalk will be added to the eastern edge of 384th Ave SE from SE Kimball Creek Drive to SE Newton Street, roughly 2,100 feet. This will complete the sidewalk gap that exists from the downtown business district to the SE Kimball Creek Drive neighborhood. Crosswalks will also be added to the SE 85th St intersection which will allow users from the adjacent neighborhood to safely access the sidewalk as well as access the bus stop located at the north west corner of the 384th Ave SE SE 85th St intersection. The width of the sidewalk will be a minimum of 6 feet.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.