City of Lakewood's Steilacoom Boulevard SW Sidewalk

P-P-199(P10)-1

P-P-199(P10)-1
Steilacoom Boulevard SW Sidewalk

87th Ave SW to Weller Rd SW

FY 2023 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $442,680

County: Pierce   |   Legislative District: 28   |   Project Length: 0.62   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency LAKEWOOD
Funding Year 2023
Program SP
Current Phase Construction
Legislative District 28
Congressional District 10
Federal Route Number 3136
Project Length 0.62 mi.
ADT 21,769
Functional Class Principal
Type of Work Pedestrian
Project Contact Troy Pokswinski
Contact Email TPokswinski@cityoflakewood.us
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 01/01/2023  
DAHP Assessment Date   10/23/2018
Predesign Approval
Design Approval 02/01/2022 12/02/2021
Bid Auth. Approval 01/16/2024 01/16/2024
Construction Approval 10/23/2024 10/25/2024
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 57,741 422,000
Construction Contract 384,939 5,239,272
Other Construction 0 0
Total Construction 442,680 5,661,272
     
Total TIB Funding 442,680 5,661,272

Local Funding Partners

Funding Amount Percent
LAKEWOOD 653,087 11.5%
WSDOT Funding 0 0.0%
 
PSRC CN Grant Award  2,263,705 40.0%
City Safety CN Grant Award  2,301,800 40.7%
 
 
 
 
 
Total Local Funding 5,218,592 92.2%

Project Description

The project will construct an ADA compliant sidewalks, bicycle lanes and vehicular facilities that will increase safety and improve access to transit. New pavement surface, pavement markings and signals will increase vehicular, pedestrian and cyclist safety through the corridor.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.