Currently 53rd Avenue NE, a connector between Sunnyside Blvd (a major arterial) and State Route 528 only has curb, gutter and sidewalk on the west side of the road. There is no curb or shoulder or sidewalk on the east side of 53rd Avenue NE in this highly urbanized neighborhood in Marysville. Therefore a shared used path is needed on the east side of 53rd between Sunnyside Blvd and SR 528.
Projects — TIB Project Information
TIB Project Information
City of Marysville's 53rd Ave NE Shared Used Path
P-P-143(P03)-1
P-P-143(P03)-1
53rd Ave NE Shared Used Path
61st St NE to SR 528
FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $320,000
County: Snohomish | Legislative District: 38 | Project Length: 600.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | MARYSVILLE |
Funding Year | 2024 |
Program | ATP |
Current Phase | Construction |
Legislative District | 38 |
Congressional District | 2 |
Federal Route Number | 2666 |
Project Length | 600.00 mi. |
ADT | 1,500 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Max Phan |
Contact Email | mphan@marysvillewa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
DAHP Assessment Date | 02/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 02/01/2023 |
Bid Auth. Approval | 12/01/2023 | 11/30/2023 |
Construction Approval | 07/18/2024 | 07/24/2024 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 28,738 | 223,937 |
Construction Contract | 291,262 | 1,812,527 |
Other Construction | 0 | 0 |
Total Construction | 320,000 | 2,036,464 |
Total TIB Funding | 320,000 | 2,036,464 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MARYSVILLE | 162,845 | 8.0% |
WSDOT Funding | 0 | 0.0% |
Federal Funds | 1,553,619 | 76.3% |
Total Local Funding | 1,716,464 | 84.3% |
Project Description
The project will complete the 53rd Avenue NE roadway section and build about 600 feet of curb, gutter, bio-retention swale and shared use path between Sunnyside Blvd and SR 528 to accommodate both pedestrians and bicyclists.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |