TIB Project Information

City of Marysville's 53rd Ave NE Shared Used Path

P-P-143(P03)-1

P-P-143(P03)-1
53rd Ave NE Shared Used Path

61st St NE to SR 528

FY 2024 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $320,000

County: Snohomish   |   Legislative District: 38   |   Project Length: 600.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency MARYSVILLE
Funding Year 2024
Program ATP
Current Phase Bid Authorization
Legislative District 38
Congressional District 2
Federal Route Number 2666
Project Length 600.00 mi.
ADT 1,500
Functional Class Collector
Type of Work Pedestrian
Project Contact Max Phan
Contact Email mphan@marysvillewa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date   02/01/2024
Predesign Approval
Design Approval 02/01/2023 02/01/2023
Bid Auth. Approval 12/01/2023 11/30/2023
Construction Approval 05/21/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 28,738 37,000
Construction Contract 291,262 375,000
Other Construction 0 0
Total Construction 320,000 412,000
     
Total TIB Funding 320,000 412,000

Local Funding Partners

Funding Amount Percent
MARYSVILLE 92,000 22.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 92,000 22.3%

Project Description

The project will complete the 53rd Avenue NE roadway section and build about 600 feet of curb, gutter, bio-retention swale and shared use path between Sunnyside Blvd and SR 528 to accommodate both pedestrians and bicyclists.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments