The intersection of 13th Street and Park Avenue is a three leg intersection that is only stop controlled on Park Avenue. It is located along the frontage of AIM Highschool and within a quarter mile of Emerson Elementary School, Hill Park, and multiple churches. The existing intersection has two non-compliant curb ramps on the north side of 13th Street and no curb ramps on the south side of the road. The City has received comments from students and other pedestrians that they do not feel safe crossing the street in this location.
Projects — TIB Project Information
TIB Project Information
City of Snohomish's 13th Street Intersection Improvements
P-P-142(P01)-1
P-P-142(P01)-1
13th Street Intersection Improvements
Park Ave
FY 2025 Active Transportation Program
Current Phase : Design
Total TIB Funding : $177,539
County: Snohomish | Legislative District: 44 | Project Length: 150.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | SNOHOMISH |
Funding Year | 2025 |
Program | ATP |
Current Phase | Design |
Legislative District | 44 |
Congressional District | 1 |
Federal Route Number | 2650 |
Project Length | 150.00 mi. |
ADT | 5,100 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Cory Morton |
Contact Email | morton@snohomishwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2024 | 12/14/2023 |
Bid Auth. Approval | 05/01/2025 | |
Construction Approval | 06/01/2025 | |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,454 | 9,946 |
Right of Way | 0 | 0 |
Total Design | 8,454 | 9,946 |
Construction Engineering | 2,125 | 2,500 |
Construction Contract | 166,960 | 196,424 |
Other Construction | 0 | 0 |
Total Construction | 169,085 | 198,924 |
Total TIB Funding | 177,539 | 208,870 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SNOHOMISH | 31,331 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 31,331 | 15.0% |
Project Description
This project will construct curb bulb outs on 13th Street at Pine Aveune to increase visibility of pedestrians and reduce the crossing distance. adding rectangular rapid flashing beacons and additional street lighting will also be installed on the eastern leg of the intersection to further increase pedestrian safety.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves vehicle and pedestrian access;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |