There are several marked crosswalks on arterials in the Town of Steilacoom that are at uncontrolled locations with significant pedestrian use. Though drivers are required to stop at crosswalks when pedestrians are present to cross them, drivers are not as compliant as when RRFBs are present. During peak traffic times, the gap for pedestrian crossing drops as low as 10%.
Projects — TIB Project Information
TIB Project Information
Town of Steilacoom's Townwide RRFB Project
P-P-133(P03)-1
P-P-133(P03)-1
Townwide RRFB Project
Steilacoom Blvd, Union Ave and Puyallup St
FY 2024 Active Transportation Program
Current Phase : Closeout
Total TIB Funding : $209,328
County: Pierce | Legislative District: 28 | Project Length: 100.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/02/2024
Project Information
Lead Agency | STEILACOOM |
Funding Year | 2024 |
Program | ATP |
Current Phase | Closeout |
Legislative District | 28 |
Congressional District | 10 |
Federal Route Number | 3136 |
Project Length | 100.00 mi. |
ADT | 7,200 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Mark Burlingame |
Contact Email | mark.burlingame@ci.steilacoom.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/23/2022 |
Bid Auth. Approval | 12/01/2023 | 11/27/2023 |
Construction Approval | 01/11/2024 | 01/12/2024 |
Project Closeout | 11/30/2024 | 11/25/2024 |
Audit Date | 12/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 29,400 | 39,000 |
Right of Way | 0 | 0 |
Total Design | 29,400 | 39,000 |
Construction Engineering | 29,400 | 23,723 |
Construction Contract | 196,680 | 215,913 |
Other Construction | 0 | 468 |
Total Construction | 226,080 | 240,104 |
Funding Surplus | - 46,152 | |
Total TIB Funding | 209,328 | 279,104 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
STEILACOOM | 69,776 | 25.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 69,776 | 25.0% |
Project Description
This project will install 3 Rectangular Rapid Flashing Beacon systems at the following locations Steilacoom Boulevard Byrd Drive Union Avenue Sequalish Street Puyallup Street/Steilacoom Blvd Starling Street
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |