The Interurban Trail is a major pedestrian/bicyclist pathway primarily running North-South from South Seattle to Southeast Pierce County. The existing crossing requires users of the Interurban Trail crossing to be inconvenienced by taking a detour of upwards to 300 feet to the nearest intersection and/or crosswalk. This detour and delay have led to significant jay walking.
Projects — TIB Project Information
TIB Project Information
City of Pacific's Interurban Trail Crossing Improvements
P-P-117(P02)-1
P-P-117(P02)-1
Interurban Trail Crossing Improvements
Ellingson Rd
FY 2025 Active Transportation Program
Current Phase : Design
Total TIB Funding : $79,240
County: King/Pierce | Legislative District: 30 | Project Length: 107.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 08/19/2025
Project Information
| Lead Agency | PACIFIC |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Design |
| Legislative District | 30 |
| Congressional District | 9 |
| Federal Route Number | 1026 |
| Project Length | 107.00 mi. |
| ADT | 13,640 |
| Functional Class | Minor |
| Type of Work | Pedestrian |
| Project Contact | Rick Gehrke |
| Contact Email | rgehrke@ci.pacific.wa.us |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 08/19/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 01/23/2024 |
| Bid Auth. Approval | 02/01/2026 | |
| Construction Approval | 02/15/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 15,210 | 16,900 |
| Right of Way | 0 | 0 |
| Total Design | 15,210 | 16,900 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 50,823 | 56,470 |
| Other Construction | 13,207 | 14,674 |
| Total Construction | 64,030 | 71,144 |
| Total TIB Funding | 79,240 | 88,044 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PACIFIC | 8,804 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 8,804 | 10.0% |
Project Description
This project constructs an enhance crossing of Ellingson Road for the Interurban Trail with a speed table, striping and rectangular rapid flashing beacon.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves vehicle and pedestrian access;
- Removes ADA barriers
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||