132nd Avenue NE is an urban minor arterial connecting LWTech and the N Rose Hill neighborhood with the regionally designated Totem Lake Urban Center. Currently there is an uncontrolled pedestrian crossing at the LWTech campus driveway (the primary campus transit stop).
Projects — TIB Project Information
TIB Project Information
City of Kirkland's Pedestrian Crossing at Lake Washington Institute of Technology
P-P-111(P08)-1
P-P-111(P08)-1
Pedestrian Crossing at Lake Washington Institute of Technology
132nd Ave NE
FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $131,355
County: King | Legislative District: 45 | Project Length: 40.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | KIRKLAND |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Construction |
| Legislative District | 45 |
| Congressional District | 1 |
| Federal Route Number | 2067 |
| Project Length | 40.00 mi. |
| ADT | 6,758 |
| Functional Class | Minor |
| Type of Work | Pedestrian |
| Project Contact | Ling Wang-Staley |
| Contact Email | lwangstaley@kirklandwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 01/24/2024 |
| Bid Auth. Approval | 01/31/2025 | 01/24/2024 |
| Construction Approval | 01/31/2025 | 12/31/2024 |
| Project Closeout | 12/31/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 35,866 | 22,330 |
| Right of Way | 0 | 0 |
| Total Design | 35,866 | 22,330 |
| Construction Engineering | 35,715 | 0 |
| Construction Contract | 193,419 | 152,000 |
| Other Construction | 0 | 0 |
| Total Construction | 229,134 | 152,000 |
| Funding Surplus | - 133,645 | |
| Total TIB Funding | 131,355 | 174,330 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KIRKLAND | 42,975 | 24.7% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 42,975 | 24.7% |
Project Description
The project includes upgrading the current uncontrolled pedestrian crossing with the addition of a Rectangular Rapid Flashing Beacon (RRFB) pedestrian crossing at Lake Washington Institute of Technology on 132nd Avenue NE.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves vehicle and pedestrian access;
- Removes ADA barriers
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||