Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Seattle's 4th Avenue S Walkway

P-P-101(P08)-1

P-P-101(P08)-1
4th Avenue S Walkway

S Royal Brougham Way to I 90 Off-Ramp

FY 2023 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $247,000

County: King   |   Legislative District: 37   |   Project Length: 0.14   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency SEATTLE
Funding Year 2023
Program SP
Current Phase Construction
Legislative District 37
Congressional District 7
Federal Route Number 1495
Project Length 0.14 mi.
ADT 26,100
Functional Class Principal
Type of Work Pedestrian
Project Contact Tonnie Roberts
Contact Email tonnie.roberts@seattle.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment IDP

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date   08/16/2022
Predesign Approval
Design Approval 07/15/2022 06/29/2022
Bid Auth. Approval 10/31/2024 10/30/2024
Construction Approval 11/21/2024 11/05/2024
Project Closeout 06/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 15,014 150,453
Construction Contract 231,986 489,117
Other Construction 0 0
Total Construction 247,000 639,570
     
Total TIB Funding 247,000 639,570

Local Funding Partners

Funding Amount Percent
SEATTLE 392,570 61.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 392,570 61.4%

Project Description

This project construct a concrete sidewalk to provide a seamless walkway between downtown, the stadium district, and numerous bus stops along the corridor. The new sidewalk on the west side of 4th Ave S will also lead directly to and from the King Street Station overpass providing access to regional transit services and intercity passenger rail. The new sidewalk will be designed to carry unusually high volumes, varying from 7 feet on typical sections to 10.5 feet near intersections. The project scope will include other pedestrian safety upgrades at intersections, including curb ramps and pedestrian push buttons on the sidewalk as well as crosswalks and stop bars within the intersections.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments