Due to previous years of bad weather, the city has seen a freeze thaw process that has caused many issues with the sidewalks especially around the downtown core area. Due to the lifting and separation of the sidewalk, it has created many tripping/fall hazards that have been compounded during winter weather. There are many areas that have crumbling and spalling concrete that needs to be addressed as well.
Projects — TIB Project Information
TIB Project Information
City of Zillah's Downtown Sidewalk
P-E-947(P05)-1
P-E-947(P05)-1
Downtown Sidewalk
6th St to 7th St First Ave to Second Ave
FY 2023 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $236,249
County: Yakima | Legislative District: 15 | Project Length: 0.16 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/17/2023
Project Information
Lead Agency | ZILLAH |
Funding Year | 2023 |
Program | SP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.16 mi. |
ADT | 2,400 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Ardele Steele |
Contact Email | ASteele@cityofzillah.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 01/17/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 02/10/2022 |
Bid Auth. Approval | 04/05/2022 | 03/30/2022 |
Construction Approval | 04/30/2022 | 05/03/2022 |
Project Closeout | 12/01/2022 | 01/05/2023 |
Audit Date | 01/17/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 28,656 | 31,747 |
Right of Way | 0 | 0 |
Total Design | 28,656 | 31,747 |
Construction Engineering | 28,656 | 25,611 |
Construction Contract | 191,025 | 205,141 |
Other Construction | 0 | 0 |
Total Construction | 219,681 | 230,752 |
Funding Increase | 6,871 | |
Funding Surplus | - 18,959 | |
Total TIB Funding | 236,249 | 262,499 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ZILLAH | 26,250 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 26,250 | 10.0% |
Project Description
This project will repair and replace segment of sidewalk.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |