TIB Project Information

City of Prosser's Old Inland Empire Highway Sidewalk

P-E-923(P01)-1

P-E-923(P01)-1
Old Inland Empire Highway Sidewalk

W C/L to Wine Country Rd

FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $168,425

County: Benton   |   Legislative District: 16   |   Project Length: 0.77   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 04/10/2024

Project Information

Lead Agency PROSSER
Funding Year 2024
Program ATP
Current Phase Construction
Legislative District 16
Congressional District 4
Federal Route Number 3743
Project Length 0.77 mi.
ADT 2,224
Functional Class Collector
Type of Work Pedestrian
Project Contact Marty Groom
Contact Email mgroom@ci.prosser.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 04/10/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date   07/23/2014
Predesign Approval
Design Approval 02/01/2023 12/16/2022
Bid Auth. Approval 03/15/2023 04/11/2023
Construction Approval 06/29/2023 07/07/2023
Project Closeout 06/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 19,673 230,100
Construction Contract 151,327 1,489,986
Other Construction 0 0
Total Construction 171,000 1,720,086
     
Funding Surplus - 2,575  
Total TIB Funding 168,425 1,720,086

Local Funding Partners

Funding Amount Percent
PROSSER 28,770 1.7%
WSDOT Funding 0 0.0%
Benton-Franklin Council of Governments 2019 STBGTAP  372,818 21.7%
BentonFranklin Council of Governments 2022 STBGTAP  234,577 13.6%
Federal Highways Administration NHFP  883,000 51.3%
Benton-Franklin Council of Governments 2023 CRP  32,496 1.9%
 
 
 
 
Total Local Funding 1,551,661 90.2%

Project Description

Imminent conflict, with vulnerable transportation users on this otherwise narrow, rural, freight road with no shoulders, bike lanes, or sidewalks, can be mitigated with this project. OIE highway is one of two well-traveled truck routes used to bring produce from nearby farms to the Citys food processing facilities, allowing local and regional freight movement without adding trips on nearby I-82. Completion of the project will improve the structural load carrying capability for OIE Highway, eliminating the need for load and width limits in the project area. The lighting, curb, bike lane, and gutter improvements will make cyclist and pedestrian movements attractive when the Prosser School District improves its property near OIE Highway and Albro Road. Providing active transportation options may reduce future motorized congestion and promote active, healthy communities on a roadway with no current pedestrian or bicycle facilities in place.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments