 Projects — TIB Project Information

TIB Project Information

City of Airway Heights's SR 2

P-E-893(P03)-1

P-E-893(P03)-1
SR 2

Hayford Rd to Deer Heights Rd

FY 2020 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $97,269

County: Spokane   |   Legislative District: 6   |   Project Length: 0.37   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 08/14/2023

Project Information

Lead Agency AIRWAY HEIGHTS
Funding Year 2020
Program SP
Current Phase Audit
Legislative District 6
Congressional District 5
Federal Route Number 0002
Project Length 0.37 mi.
ADT 31,000
Functional Class Principal
Type of Work Pedestrian
Project Contact Kevin Anderson
Contact Email kanderson@cawh.org
TIB Engineer Andrew Beagle
Last Payment Date 08/14/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/15/2019 10/21/2019
Bid Auth. Approval 04/30/2022 10/27/2022
Construction Approval 11/30/2022 12/14/2022
Project Closeout 09/30/2023 08/08/2023
Audit Date   08/14/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 9,531 45,774
Right of Way 0 0
Total Design 9,531 45,774
     
Construction Engineering 9,530 54,173
Construction Contract 78,208 329,021
Other Construction 0 0
Total Construction 87,738 383,194
     
Total TIB Funding 97,269 428,968

Local Funding Partners

Funding Amount Percent
AIRWAY HEIGHTS 80,138 18.7%
WSDOT Funding 0 0.0%
Spokane Regional Transportation Council  251,561 58.6%
 
 
 
 
 
 
 
Total Local Funding 331,699 77.5%

Project Description

The proposed pathway on the north side of Highway 2 will complete a shared use pathway that extends west along Highway 2 which connects to the City sidewalk at Garfield Road, and continues for the remainder of the City limits. The path along the south side of Highway 2 will complete the current sidewalk east to the Cinema. Having sidewalks on both sides of the road completed will ensure that crossing Highway 2 at an unsignalized and dangerous intersection is not necessary for all non-motorized travel including residents with disabilities.

Project Pictures

Project Delays

Delay Type Resolution Date Comments
Coordination Issues
Level 2 Board Delay
11/01/2022 This project is a federally funded project waiting for right of way certification and oblligation of construction funds before it can be advertised.

Project Payments