The existing streets currently have a paved shoulder of 2 feet. At most locations the ground slopes steeply beyond the pavement edge making it difficult to safely accommodate pedestrians outside of traveled way. When snow is present the problem is worse. Un-controlled on-street parking adds to this problem as well. This sidewalk connection was identified by the Towns Non-Motorized Transportation Plan as a high priority to make this connection between previously constructed sidewalk and trail improvements. The proposed sidewalks provide a safe ADA accessible pedestrian corridor separated from traffic that connects existing sidewalks and provides pedestrian connectivity between the Central Business District (CBD), residential area, tourist facilities including a campground and museum. The sidewalk will also serve as a pedestrian bypass for hte congested SR 20 corridor one block south. The project will also install an infiltration storm drainage system minimizing runoff and erosion.
Projects — TIB Project Information
TIB Project Information
Town of Winthrop's Castle Avenue Sidewalk
P-E-887(P01)-1
P-E-887(P01)-1
Castle Avenue Sidewalk
Roses Hill Rd to Bridge Street Vicinity
FY 2023 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $661,822
County: Okanogan | Legislative District: 12 | Project Length: 0.47 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/15/2024
Project Information
| Lead Agency | WINTHROP | 
| Funding Year | 2023 | 
| Program | SP | 
| Current Phase | Audit | 
| Legislative District | 12 | 
| Congressional District | 4 | 
| Federal Route Number | 9999 | 
| Project Length | 0.47 mi. | 
| ADT | 750 | 
| Functional Class | TIB Arterial | 
| Type of Work | Pedestrian | 
| Project Contact | Pete Cowger | 
| Contact Email | pcowger@varela-engr.com | 
| TIB Engineer | Andrew Beagle | 
| Last Payment Date | 03/15/2024 | 
| Cultural Resource Assessment | CRA | 
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/19/2021 | |
| Delayed Project Date | 07/01/2024 | |
| DAHP Assessment Date | 03/24/2023 | |
| Predesign Approval | ||
| Design Approval | 02/01/2022 | 01/25/2022 | 
| Bid Auth. Approval | 02/15/2023 | 06/26/2023 | 
| Construction Approval | 07/10/2023 | 07/19/2023 | 
| Project Closeout | 02/15/2024 | 03/06/2024 | 
| Audit Date | 03/15/2024 | |
| Withdrawn Date | 
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 | 
| Design Study | 0 | 0 | 
| Total Predesign | 0 | 0 | 
| Special Study | 0 | 0 | 
| Design | 65,931 | 89,044 | 
| Right of Way | 0 | 0 | 
| Total Design | 65,931 | 89,044 | 
| Construction Engineering | 65,931 | 76,183 | 
| Construction Contract | 439,540 | 545,672 | 
| Other Construction | 0 | 0 | 
| Total Construction | 505,471 | 621,855 | 
| Funding Increase | 90,420 | |
| Total TIB Funding | 661,822 | 710,899 | 
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WINTHROP | 49,077 | 6.9% | 
| WSDOT Funding | 0 | 0.0% | 
| Total Local Funding | 49,077 | 6.9% | 
Project Description
***Board Approved Change 1/27*** Install sidewalk on north side of Castle Avenue from Roses Hill Road to Bridge Street Vicinity (approximately within 100'). Reduce pavement width to 24'.
Existing Condition
Project Benefits
- Improves pedestrian safety;
 - Removes ADA barriers
 
Project Delays
| Delay Type | Resolution Date | Comments | 
|---|---|---|
No delayed project history.  | 
                                                    ||