A pedestrian and bicycle gap from the Twisp River Bridge to the northern city limit exists.
Projects — TIB Project Information
TIB Project Information
Town of Twisp's North End SR 20 PedestrianBike Path
P-E-886(P02)-1
P-E-886(P02)-1
North End SR 20 PedestrianBike Path
Twisp River Br to Days Ln
FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $592,470
County: Okanogan | Legislative District: 7 | Project Length: 2,059.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/12/2025
Project Information
| Lead Agency | TWISP |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Construction |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 0020 |
| Project Length | 2059.00 mi. |
| ADT | 5,563 |
| Functional Class | Minor |
| Type of Work | Pedestrian |
| Project Contact | Andrew Denham |
| Contact Email | publicworks@townoftwisp.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 06/12/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 01/01/2025 | |
| DAHP Assessment Date | 12/05/2023 | |
| Predesign Approval | ||
| Design Approval | 01/01/2024 | 12/19/2023 |
| Bid Auth. Approval | 06/30/2024 | 06/28/2024 |
| Construction Approval | 10/15/2024 | 12/17/2024 |
| Project Closeout | 12/31/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 35,405 | 184,823 |
| Construction Contract | 574,131 | 1,429,664 |
| Other Construction | 1,836 | 0 |
| Total Construction | 611,372 | 1,614,487 |
| Funding Surplus | - 18,902 | |
| Total TIB Funding | 592,470 | 1,614,487 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| TWISP | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| WSDOT | 1,022,017 | 63.3% |
| Total Local Funding | 1,022,017 | 63.3% |
Project Description
Extend a bike lane on the northbound side and a shared-use path on the southbound side of SR20. Intersection radii will be improved for crosswalks. Roadway will need realignment to accomodate proposed improvements.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||