Intersection Vicinity

FY 2025 Active Transportation Program
Current Phase : Design
Total TIB Funding : $136,000

County: Okanogan   |   Legislative District: 7   |   Project Length: 0.16   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency PATEROS
Funding Year 2025
Program ATP
Current Phase Design
Legislative District 7
Congressional District 0
Federal Route Number 9999
Project Length 0.16 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Jord Wilson
Contact Email paterosparks@outlook.com
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/08/2024 02/20/2024
Bid Auth. Approval 07/15/2024
Construction Approval 08/05/2024
Project Closeout 12/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 8,100 8,100
Right of Way 0 0
Total Design 8,100 8,100
     
Construction Engineering 8,100 8,100
Construction Contract 54,000 54,000
Other Construction 65,800 65,800
Total Construction 127,900 127,900
     
Total TIB Funding 136,000 136,000

Local Funding Partners

Funding Amount Percent
PATEROS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Intersection reconfiguration using resin bonded stone surfacing, striping and other low-cost materials

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.