Problem intersection area for movement and safety.
Projects — TIB Project Information
TIB Project Information
City of Pateros's Resin Bonded Stone Surfacing Pilot
P-E-883(P06)-1
P-E-883(P06)-1
Resin Bonded Stone Surfacing Pilot
Intersection Vicinity
FY 2025 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $71,906
County: Okanogan | Legislative District: 7 | Project Length: 0.16 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/30/2025
Project Information
| Lead Agency | PATEROS |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Audit |
| Legislative District | 7 |
| Congressional District | 0 |
| Federal Route Number | 9999 |
| Project Length | 0.16 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Jord Wilson |
| Contact Email | paterosparks@outlook.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 06/30/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/08/2024 | 02/20/2024 |
| Bid Auth. Approval | 07/15/2024 | 12/03/2024 |
| Construction Approval | 08/05/2024 | 12/03/2024 |
| Project Closeout | 03/01/2025 | 06/30/2025 |
| Audit Date | 06/30/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 8,100 | 8,640 |
| Right of Way | 0 | 0 |
| Total Design | 8,100 | 8,640 |
| Construction Engineering | 8,100 | 0 |
| Construction Contract | 54,000 | 58,049 |
| Other Construction | 65,800 | 5,217 |
| Total Construction | 127,900 | 63,266 |
| Funding Surplus | - 64,094 | |
| Total TIB Funding | 71,906 | 71,906 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PATEROS | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Intersection reconfiguration using resin bonded stone surfacing, striping and other low-cost materials
Existing Condition
Project Benefits
- Material test and improved intersection configuration.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||