This project either adds new or removes/replaces 46 ADA ramps in Coulee Dam per the attached exhibit. The goal with this project is to meet ADA ramp requirements in this area then submit for preservation funding the following year. The need is very straightforward, the City must meet the 2010 ADA requirements to the maximum extent feasible and either ADA ramps do not exist in these areas or the existing ramps do not comply with current standards. Several ramp replacements occur around the schools, commercial areas, and on the State Highway. This project will be advertised as a single package with the Safe Routes to School project that was awarded to the City earlier this year.
Projects — TIB Project Information
TIB Project Information
Town of Coulee Dam's ADA Ramp Upgrades
P-E-878(P06)-1
P-E-878(P06)-1
ADA Ramp Upgrades
Multiple Locations
FY 2025 Active Transportation Program
Current Phase : Design
Total TIB Funding : $481,406
County: Okanogan/Douglas/Grant | Legislative District: 7 | Project Length: 1.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 06/03/2024
Project Information
Lead Agency | COULEE DAM |
Funding Year | 2025 |
Program | ATP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 1.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Stefani Bowden |
Contact Email | cdclerk@couleedam.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 06/03/2024 |
Cultural Resource Assessment | BER |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2024 | 02/02/2024 |
Bid Auth. Approval | 10/30/2024 | |
Construction Approval | 12/15/2024 | |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 64,805 | 64,805 |
Right of Way | 0 | 0 |
Total Design | 64,805 | 64,805 |
Construction Engineering | 46,289 | 46,289 |
Construction Contract | 370,312 | 370,312 |
Other Construction | 0 | 0 |
Total Construction | 416,601 | 416,601 |
Total TIB Funding | 481,406 | 481,406 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COULEE DAM | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
The solution is to install or upgrade existing ramps to comply with the ADA standards and move forward with phase 2 of the project, which is preservation funding for this area of Town.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |