Town of Coulee Dam's ADA Ramp Upgrades

P-E-878(P06)-1

P-E-878(P06)-1
ADA Ramp Upgrades

Multiple Locations

FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $416,939

County: Okanogan/Douglas/Grant   |   Legislative District: 7   |   Project Length: 1.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 09/17/2025

Project Information

Lead Agency COULEE DAM
Funding Year 2025
Program ATP
Current Phase Construction
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 1.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Stefani Bowden
Contact Email cdclerk@couleedam.org
TIB Engineer Andrew Beagle
Last Payment Date 09/17/2025
Cultural Resource Assessment BER

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date   02/28/2025
Predesign Approval
Design Approval 02/15/2024 02/02/2024
Bid Auth. Approval 03/30/2025 05/07/2025
Construction Approval 06/04/2025 07/21/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 50,134 50,126
Right of Way 0 0
Total Design 50,134 50,126
     
Construction Engineering 35,810 84,800
Construction Contract 286,477 273,345
Other Construction 0 13,667
Total Construction 322,287 371,812
     
Funding Increase 44,518  
Total TIB Funding 416,939 421,938

Local Funding Partners

Funding Amount Percent
COULEE DAM 4,999 1.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 4,999 0.0%

Project Description

The solution is to install or upgrade existing ramps to comply with the ADA standards and move forward with phase 2 of the project, which is preservation funding for this area of Town.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.