Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Royal City's Apple Avenue NE Sidewalks

P-E-864(P01)-1

P-E-864(P01)-1
Apple Avenue NE Sidewalks

Camelia St to Slate Ln NE

FY 2023 Sidewalk Program
Current Phase : Design
Total TIB Funding : $298,396

County: Grant   |   Legislative District: 13   |   Project Length: 0.31   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency ROYAL CITY
Funding Year 2023
Program SP
Current Phase Design
Legislative District 13
Congressional District 4
Federal Route Number 9999
Project Length 0.31 mi.
ADT 1,100
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact John Lasen
Contact Email rcpw@royalcitywa.org
TIB Engineer Jonathan Heusman
Last Payment Date

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 01/01/2022 12/22/2021
Bid Auth. Approval 03/15/2023
Construction Approval 04/15/2023
Project Closeout 07/31/2023
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 29,840 31,410
Right of Way 0 0
Total Design 29,840 31,410
     
Construction Engineering 29,840 31,410
Construction Contract 238,716 251,280
Other Construction 0 0
Total Construction 268,556 282,690
     
Total TIB Funding 298,396 314,100

Local Funding Partners

Funding Amount Percent
ROYAL CITY 15,704 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 15,704 5.0%

Project Description

This project will fill two gaps in sidewalk of Apple Avenue Ne. The first gap will connect existing sidewalk on Camelia Street NE to the existing sidewalk south of Cherry Street NE. The second gap will connect existing sidewalk north of Poplar Street NE with sidewalk at the intersection of Slate Lane NE and Apple Avenue NE. The sidewalk and ADA-compliant ramps will provide a clear, safe, and accessible route for pedestrians.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments