Apple Avenue (Road F) serves as a minor collector to multi-family housing, single-family residential, the Royal City School District and to the Central Business District. There is approximately 1,300 linear feet of existing sidewalk adjacent to several existing developments on the west side of Apple Avenue. The distance between Camelia Street and Slate Lane is approximately 3,000 linear feet and is missing several segments of sidewalk due to property that is undeveloped and property that was developed prior to Apple Avenue becoming a city street. The lack of sidewalk along this stretch forces pedestrians to walk in the street or on the gravel shoulder. Given that there are existing residences and that the area is expected to grow in single-family residential developments, the need to complete the sidewalk corridor and provide Americans with Disabilities Act (ADA) ramps at intersections to provide ADA-compliant connectivity between streets for pedestrians is significant.
Projects — TIB Project Information
TIB Project Information
City of Royal City's Apple Avenue NE Sidewalks
P-E-864(P01)-1
P-E-864(P01)-1
Apple Avenue NE Sidewalks
Camelia St to Slate Ln NE
FY 2023 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $348,396
County: Grant | Legislative District: 13 | Project Length: 0.31 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/14/2024
Project Information
Lead Agency | ROYAL CITY |
Funding Year | 2023 |
Program | SP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.31 mi. |
ADT | 1,100 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | John Lasen |
Contact Email | rcpw@royalcitywa.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/14/2024 |
Cultural Resource Assessment | IDP |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 06/16/2023 | |
Predesign Approval | ||
Design Approval | 01/01/2022 | 12/22/2021 |
Bid Auth. Approval | 04/30/2023 | 06/13/2023 |
Construction Approval | 07/07/2023 | 08/01/2023 |
Project Closeout | 12/31/2024 | 11/08/2024 |
Audit Date | 11/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 29,840 | 31,000 |
Right of Way | 0 | 0 |
Total Design | 29,840 | 31,000 |
Construction Engineering | 29,840 | 25,237 |
Construction Contract | 238,716 | 375,430 |
Other Construction | 0 | 0 |
Total Construction | 268,556 | 400,667 |
Funding Increase | 50,000 | |
Total TIB Funding | 348,396 | 431,667 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROYAL CITY | 83,271 | 19.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 83,271 | 19.3% |
Project Description
This project will fill two gaps in sidewalk of Apple Avenue Ne. The first gap will connect existing sidewalk on Camelia Street NE to the existing sidewalk south of Cherry Street NE. The second gap will connect existing sidewalk north of Poplar Street NE with sidewalk at the intersection of Slate Lane NE and Apple Avenue NE. The sidewalk and ADA-compliant ramps will provide a clear, safe, and accessible route for pedestrians.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |