TIB Project Information

City of Ritzville's 6th Avenue Sidewalk

P-E-845(P03)-1

P-E-845(P03)-1
6th Avenue Sidewalk

Division St to Chelan St

FY 2024 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $378,528

County: Adams   |   Legislative District: 9   |   Project Length: 990.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 02/13/2024

Project Information

Lead Agency RITZVILLE
Funding Year 2024
Program ATP
Current Phase Construction
Legislative District 9
Congressional District 4
Federal Route Number 9999
Project Length 990.00 mi.
ADT 550
Functional Class Collector
Type of Work Pedestrian
Project Contact Scott Yaeger
Contact Email scotty@co.adams.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 02/13/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/15/2022
Bid Auth. Approval 05/15/2024 05/22/2024
Construction Approval 06/30/2024 07/17/2024
Project Closeout 09/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 48,176 63,000
Right of Way 0 0
Total Design 48,176 63,000
     
Construction Engineering 43,578 37,968
Construction Contract 301,099 306,500
Other Construction 0 0
Total Construction 344,677 344,468
     
Funding Surplus - 14,325  
Total TIB Funding 378,528 407,468

Local Funding Partners

Funding Amount Percent
RITZVILLE 28,940 7.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 28,940 7.1%

Project Description

The project replaces the existing sidewalk sections as needed to match existing width of 5' and adds ADA ramps at the required intersection. The project also installs striping at appropriate locations and addresses obstructions as needed.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.