Since 2012, there were 10 veh-ped crashes (1 fatal, 3 serious injury) on this busy commercial corridor wotj 19,400 ADT. The street is 60 feet wide with 5 lanes, has Transit stops for Route 90 serves low-income residential neighborhood as well.
Projects — TIB Project Information
TIB Project Information
City of Spokane Valley's Sprague Ave. Pedestrian Crossings
P-E-208(P10)-1
P-E-208(P10)-1
Sprague Ave. Pedestrian Crossings
Chronicle Rd and McKinnon Rd
FY 2025 Active Transportation Program
Current Phase : Design
Total TIB Funding : $479,588
County: Spokane | Legislative District: 4 | Project Length: 60.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/27/2024
Project Information
Lead Agency | SPOKANE VALLEY |
Funding Year | 2025 |
Program | ATP |
Current Phase | Design |
Legislative District | 4 |
Congressional District | 5 |
Federal Route Number | 3840 |
Project Length | 60.00 mi. |
ADT | 19,400 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Adam Jackson |
Contact Email | ajackson@spokanevalleywa.gov |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/27/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2024 | 12/20/2023 |
Bid Auth. Approval | 02/01/2025 | |
Construction Approval | 04/01/2025 | |
Project Closeout | 07/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 51,384 | 71,367 |
Right of Way | 0 | 0 |
Total Design | 51,384 | 71,367 |
Construction Engineering | 46,572 | 64,684 |
Construction Contract | 381,632 | 530,045 |
Other Construction | 0 | 0 |
Total Construction | 428,204 | 594,729 |
Total TIB Funding | 479,588 | 666,096 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE VALLEY | 186,508 | 28.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 186,508 | 28.0% |
Project Description
Two new marked crossings with pedestrian refuge islands and rectangular rapid flashing beacon signals are proposed at the mid-way points between the existing signalized intersections at Custer Rd. and at Fancher Rd.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |