Since 2012, there were 10 veh-ped crashes (1 fatal, 3 serious injury) on this busy commercial corridor wotj 19,400 ADT. The street is 60 feet wide with 5 lanes, has Transit stops for Route 90 serves low-income residential neighborhood as well.
Projects — TIB Project Information
TIB Project Information
City of Spokane Valley's Sprague Ave. Pedestrian Crossings
P-E-208(P10)-1
P-E-208(P10)-1
Sprague Ave. Pedestrian Crossings
Chronicle Rd and McKinnon Rd
FY 2025 Active Transportation Program
Current Phase : Audit
Total TIB Funding : $360,899
County: Spokane | Legislative District: 4 | Project Length: 120.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/30/2025
Project Information
| Lead Agency | SPOKANE VALLEY |
| Funding Year | 2025 |
| Program | ATP |
| Current Phase | Audit |
| Legislative District | 4 |
| Congressional District | 5 |
| Federal Route Number | 3840 |
| Project Length | 120.00 mi. |
| ADT | 19,400 |
| Functional Class | Principal |
| Type of Work | Pedestrian |
| Project Contact | Adam Jackson |
| Contact Email | ajackson@spokanevalleywa.gov |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 09/30/2025 |
| Cultural Resource Assessment | IDP |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | 01/28/2025 | |
| Predesign Approval | ||
| Design Approval | 01/01/2024 | 12/20/2023 |
| Bid Auth. Approval | 02/01/2025 | 01/29/2025 |
| Construction Approval | 04/01/2025 | 03/04/2025 |
| Project Closeout | 07/31/2025 | 09/24/2025 |
| Audit Date | 09/30/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 51,384 | 34,790 |
| Right of Way | 0 | 25,450 |
| Total Design | 51,384 | 60,240 |
| Construction Engineering | 46,572 | 62,924 |
| Construction Contract | 381,632 | 400,245 |
| Other Construction | 0 | 8,352 |
| Total Construction | 428,204 | 471,521 |
| Funding Surplus | - 118,689 | |
| Total TIB Funding | 360,899 | 531,761 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SPOKANE VALLEY | 170,862 | 32.1% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 170,862 | 32.1% |
Project Description
Two new marked crossings with pedestrian refuge islands and rectangular rapid flashing beacon signals are proposed at the mid-way points between the existing signalized intersections at Custer Rd. and at Fancher Rd.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||