The amount requested in this Sidewalk Program application is the sidewalk replacement cost of a larger reconstruction project. Roadway reconstruction is funded by the Surface Transportation Program. The sidewalk elements included in this application include ADA improvements, sidewalk, and bulb-outs necessary to meet intermodal transportation needs within the downtown core. These improvements are a continuation of the Citys downtown revitalization multi-phased project which intends to increase economic stability by replacing aging and nonscript infrastructure. The improvements will construct complete streets elements to encourage intermodal transportation and enhance pedestrian safety.
Projects — TIB Project Information
TIB Project Information
City of Sunnyside's 6th Street
P-E-179(P04)-1
P-E-179(P04)-1
6th Street
North Ave to Decatur Ave
FY 2023 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $357,900
County: Yakima | Legislative District: 15 | Project Length: 0.41 | TIB Engineer: Jonathan Heusman | Last Payment Date: 03/17/2025
Project Information
| Lead Agency | SUNNYSIDE |
| Funding Year | 2023 |
| Program | SP |
| Current Phase | Audit |
| Legislative District | 15 |
| Congressional District | 4 |
| Federal Route Number | 6335 |
| Project Length | 0.41 mi. |
| ADT | 8,900 |
| Functional Class | Minor |
| Type of Work | Pedestrian |
| Project Contact | Shane Fisher |
| Contact Email | sfisher@sunnyside-wa.gov |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 03/17/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/19/2021 | |
| Delayed Project Date | 01/01/2023 | |
| DAHP Assessment Date | 10/20/2014 | |
| Predesign Approval | ||
| Design Approval | 01/01/2022 | 12/27/2021 |
| Bid Auth. Approval | 07/08/2022 | 08/01/2022 |
| Construction Approval | 09/15/2022 | 10/25/2022 |
| Project Closeout | 12/31/2024 | 03/14/2025 |
| Audit Date | 03/17/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 37,647 | 444,000 |
| Construction Contract | 289,593 | 3,884,517 |
| Other Construction | 0 | 0 |
| Total Construction | 327,240 | 4,328,517 |
| Funding Increase | 30,660 | |
| Total TIB Funding | 357,900 | 4,328,517 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SUNNYSIDE | 406,352 | 9.4% |
| WSDOT Funding | 0 | 0.0% |
| STP Funds | 3,564,265 | 82.3% |
| Total Local Funding | 3,970,617 | 91.7% |
Project Description
This project will include new sidewalk infrastructure and ADA ramps, a railroad crossing treatment, and bulbouts.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||