Haven St. is an existing Principal Arterial and high traffic corridor and Spokane Transit bus route uses this street. The corridor includes numerous nearby commercial/business destinations as well as a large Spokane School District education campus approximately one block from Haven St. that includes Shaw Middle School, Newtech Skill Center, Regal Elementary School and School District offices and operations facilities. Additionally, the Spokane-Hillyard Library and Northeast Community Center is located just west of the education campus.There are no existing sidewalks along the westerly side of Haven St. for the three block stretch from Heroy Ave. to Rockwell Ave. creating a deficient condition for pedestrian access to transit stops, schools and businesses.
Projects — TIB Project Information
TIB Project Information
City of Spokane's Haven Street Sidewalk
P-E-165(P10)-1
P-E-165(P10)-1
Haven Street Sidewalk
Rockwell Ave to Heroy Ave
FY 2023 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $177,348
County: Spokane | Legislative District: 3 | Project Length: 0.18 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/29/2024
Project Information
Lead Agency | SPOKANE |
Funding Year | 2023 |
Program | SP |
Current Phase | Construction |
Legislative District | 3 |
Congressional District | 5 |
Federal Route Number | 3985 |
Project Length | 0.18 mi. |
ADT | 14,200 |
Functional Class | Principal |
Type of Work | Pedestrian |
Project Contact | Kevin Picanco |
Contact Email | kpicanco@spokanecity.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/29/2024 |
Cultural Resource Assessment | IDP |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 10/30/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 04/07/2022 |
Bid Auth. Approval | 09/01/2023 | 10/30/2023 |
Construction Approval | 11/30/2023 | 12/14/2023 |
Project Closeout | 08/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 19,594 | 32,566 |
Right of Way | 0 | 0 |
Total Design | 19,594 | 32,566 |
Construction Engineering | 24,492 | 36,332 |
Construction Contract | 163,284 | 214,378 |
Other Construction | 0 | 0 |
Total Construction | 187,776 | 250,710 |
Funding Surplus | - 30,022 | |
Total TIB Funding | 177,348 | 283,276 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE | 105,928 | 37.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 105,928 | 37.4% |
Project Description
Install infill separated sidewalk and requisite ADA ramps along the westerly side of Haven St. where no sidewalk exists today.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |