Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Spokane's North River Drive

P-E-165(P09)-1

P-E-165(P09)-1
North River Drive

Washington St to 800 ft E

FY 2021 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $373,674

County: Spokane   |   Legislative District: 3   |   Project Length: 0.17   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 05/15/2023

Project Information

Lead Agency SPOKANE
Funding Year 2021
Program SP
Current Phase Audit
Legislative District 3
Congressional District 5
Federal Route Number 3860
Project Length 0.17 mi.
ADT 6,269
Functional Class Collector
Type of Work Pedestrian
Project Contact Kevin Picanco
Contact Email kpicanco@spokanecity.org
TIB Engineer Andrew Beagle
Last Payment Date 05/15/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2022  
DAHP Assessment Date   05/26/2021
Predesign Approval
Design Approval 03/01/2020 02/19/2020
Bid Auth. Approval 08/01/2021 06/03/2021
Construction Approval 07/01/2021 07/22/2021
Project Closeout 04/25/2023 05/05/2023
Audit Date   05/15/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 35,398 131,140
Right of Way 0 37,186
Total Design 35,398 168,326
     
Construction Engineering 47,557 144,504
Construction Contract 317,045 1,055,266
Other Construction 0 7,194
Total Construction 364,602 1,206,964
     
Funding Surplus - 26,326  
Total TIB Funding 373,674 1,375,290

Local Funding Partners

Funding Amount Percent
SPOKANE 1,001,616 72.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,001,616 72.8%

Project Description

This project would include sidewalk installation on each side of the street. Topography of the roadway will not facilitate separation the full distance. Acquisition of right of way on the south side near Washington Street will be requisite for sidewalk installation. The city proposes installation of an eight foot wide sidewalk on each side with separation where possible on the north side. The project adds curbing and stormwater drain facilities along with the sidewalks.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments