Spokane County's Rowan Ave. ADA Ramp Replacement

P-E-032(P09)-1

P-E-032(P09)-1
Rowan Ave. ADA Ramp Replacement

Starr Rd to Idaho Rd

FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $336,437

County: Spokane   |   Legislative District: 4   |   Project Length: 5,234.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/04/2024

Project Information

Lead Agency SPOKANE COUNTY
Funding Year 2025
Program ATP
Current Phase Construction
Legislative District 4
Congressional District 5
Federal Route Number 4190
Project Length 5234.00 mi.
ADT 829
Functional Class Collector
Type of Work Pedestrian
Project Contact Jami Hayes
Contact Email jhayes@spokanecounty.org
TIB Engineer Andrew Beagle
Last Payment Date 11/04/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2024 12/21/2023
Bid Auth. Approval 07/01/2024 08/08/2024
Construction Approval 08/25/2024 08/29/2024
Project Closeout 11/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 55,400 55,000
Right of Way 0 0
Total Design 55,400 55,000
     
Construction Engineering 55,400 55,000
Construction Contract 314,560 336,456
Other Construction 0 0
Total Construction 369,960 391,456
     
Funding Surplus - 88,923  
Total TIB Funding 336,437 446,456

Local Funding Partners

Funding Amount Percent
SPOKANE COUNTY 110,019 24.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 110,019 26.7%

Project Description

Approximately 27 ADA ramps will be constructed to current standards.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments