City of North Bonneville's Complete Streets Award
C-W-973(001)-1
C-W-973(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $125,000
County: Skamania | Legislative District: 14 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/27/2017
Project Information
Lead Agency | NORTH BONNEVILLE |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 14 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Steve Hasson |
Contact Email | Steve@northbonneville.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | 02/27/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/07/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/07/2017 | |
Bid Auth. Approval | 02/15/2017 | |
Construction Approval | 02/15/2017 | 02/07/2017 |
Project Closeout | 02/07/2020 | 01/06/2020 |
Audit Date | 01/07/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 125,000 | 125,000 |
Other Construction | 0 | 0 |
Total Construction | 125,000 | 125,000 |
Total TIB Funding | 125,000 | 125,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTH BONNEVILLE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Trails and Crosswalk | Pedestrian | Dec 2016 | $65,000 | $ 0 | |
Project consists of asphalt walkways, 4 ADA ramps and crosswalk striping for the two crossings. Project also connects new City Trail Hub to new pedestrian bridges and access to National Forest. | |||||
City Park Intersection Improvements | Pedestrian | Dec 2016 | $35,000 | $75,132 | |
Project Consists of installing 3 stop signs, 2 short asphalt walkways, 2 ADA ramps, and crosswalk striping. The project also connects existing pathwyas and provides safer access between popular points. | |||||
City Pathway Repair | Pedestrian | Dec 2016 | $90,000 | $49,868 | |
Repair root heave damage and deterioiration of the City pathway system improving safety. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |