 Projects — TIB Project Information

TIB Project Information

City of Long Beach's Complete Streets Award

C-W-970(001)-1

C-W-970(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $75,000

County: Pacific   |   Legislative District: 19   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency LONG BEACH
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Ariel Smith
Contact Email asmith@longbeachwa.gov
TIB Engineer Chris Langhoff
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2022
Delayed Project Date 03/30/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 04/20/2022
Bid Auth. Approval 05/01/2022 04/20/2022
Construction Approval 05/01/2022 04/20/2022
Project Closeout 05/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 75,000 75,000
Other Construction 0 0
Total Construction 75,000 75,000
     
Total TIB Funding 75,000 75,000

Local Funding Partners

Funding Amount Percent
LONG BEACH 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
North End Improvements Pedestrian Mar 2022 $75,000 $ 0
The city of Long Beach has been working on an improvement project for nearly two-years. There are five blocks between 21st NE and 26th NE that need lighting and sidewalks. This Is a high traffic area as it links residential and short-term rentals to the golf course. The city has purchased the light poles, globes and has a bid to start the electrical work. In the last year the city has also completed stormwater Improvements. This work has amounted to roughly $78,000. The last portion of the project Is the sidewalks (estimated to be $110,000). This money would be used to literally complete the street. The sidewalks would meet ADA requirements and be a great addition to the north end of Long Beach. If we were awarded $75,000 we would use local funds to finish the project. This is our number one priority.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments