 Projects — TIB Project Information

TIB Project Information

City of Ridgefield's Hillhurst Pedestrian Improvements

C-W-950(001)-1

C-W-950(001)-1
Hillhurst Pedestrian Improvements

Multiple Locations

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $260,000

County: Clark   |   Legislative District: 18   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 11/04/2024

Project Information

Lead Agency RIDGEFIELD
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 18
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Chuck Green
Contact Email Chuck.Green@ridgefieldwa.us
TIB Engineer Chris Langhoff
Last Payment Date 11/04/2024
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/15/2024 03/26/2024
Bid Auth. Approval 05/15/2024 06/17/2024
Construction Approval 07/29/2024 07/19/2024
Project Closeout 01/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 24,000 31,300
Right of Way 0 0
Total Design 24,000 31,300
     
Construction Engineering 12,320 27,000
Construction Contract 223,680 290,000
Other Construction 0 0
Total Construction 236,000 317,000
     
Total TIB Funding 260,000 348,300

Local Funding Partners

Funding Amount Percent
RIDGEFIELD 88,300 25.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 88,300 25.4%

Project Description

This project will install a high intensity actuated crosswalk (HAWK) signal, speed reader boards, school zone signage, rectangular rapid flashing beacon (RRFB) and ADA compliant ramps.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.