Town of La Conner's Pedestrian Improvements
C-W-834(001)-1
C-W-834(001)-1
Pedestrian Improvements
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Closeout
Total TIB Funding : $32,116
County: Skagit | Legislative District: 10 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 12/02/2024
Project Information
Lead Agency | LA CONNER |
Funding Year | 2026 |
Program | CSP |
Current Phase | Closeout |
Legislative District | 10 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Brian Lease |
Contact Email | publicworks@townoflaconner.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 12/02/2024 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 03/22/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 04/15/2024 | 03/28/2024 |
Bid Auth. Approval | 06/28/2024 | 06/22/2024 |
Construction Approval | 07/30/2024 | 07/31/2024 |
Project Closeout | 12/31/2024 | 11/19/2024 |
Audit Date | 12/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 240,000 | 29,817 |
Other Construction | 0 | 6,970 |
Total Construction | 240,000 | 36,787 |
Funding Increase | 1,798 | |
Funding Surplus | - 209,682 | |
Total TIB Funding | 32,116 | 36,787 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LA CONNER | 4,671 | 12.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 4,671 | 12.7% |
Project Description
The project consists of installing RRFB's on Maple Avenue at the Caledonia Street, Rainier Street and Talbott Street intersections.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |