 Projects — TIB Project Information

TIB Project Information

City of Langley's Complete Streets Award

C-W-828(001)-1

C-W-828(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000

County: Island   |   Legislative District: 10   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 02/27/2017

Project Information

Lead Agency LANGLEY
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 10
Congressional District 2
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Stan Berryman
Contact Email sberryman@langleywa.org
TIB Engineer Chris Langhoff
Last Payment Date 02/27/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   02/07/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/07/2017
Bid Auth. Approval 02/15/2017
Construction Approval 02/15/2017 02/07/2017
Project Closeout 01/31/2020 02/03/2020
Audit Date   02/04/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 250,000 250,000
Other Construction 0 0
Total Construction 250,000 250,000
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
LANGLEY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
1st Street - Wharf Drive to Anthes Avenue Pedestrian; Bicycle; Aesthetics Dec 2016 $250,000 $2,500,000
Provide five raised pedestrian crossings; replace approximately 400 feet of curb, gutter and sidewalk and 11 ADA ramps, Create pedestrian plaza at Thomas Hladky Park. Provide ADA accessibility and pedestrian lighting to Whale Bell Park. Furnish and install 3 bicycle racks. Modify street parking from angle parking to parallel improving storefront visibility and adding new ADA compliant sidewalk.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.