City of Olympia's Complete Streets Award

C-W-195(003)-1

C-W-195(003)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $300,000

County: Thurston   |   Legislative District: 22   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 07/15/2022

Project Information

Lead Agency OLYMPIA
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 22
Congressional District 10
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Sophie Stimson
Contact Email sstimson@ci.olympia.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 07/15/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2022
Delayed Project Date 03/30/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 07/07/2022
Bid Auth. Approval 05/01/2022 07/07/2022
Construction Approval 05/01/2022 07/07/2022
Project Closeout 08/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 300,000 300,000
Other Construction 0 0
Total Construction 300,000 300,000
     
Total TIB Funding 300,000 300,000

Local Funding Partners

Funding Amount Percent
OLYMPIA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Southeast to Downtown Bike Corridor Bicycle Mar 2022 $300,000 $ 0
$1M project includes a crossing island, an RRFB, segments of buffered bike lane, signs, and markings. Project connects regional trail system to downtown.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.