Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Longview's 18th Avenue ADA Ramps

C-W-187(002)-1

C-W-187(002)-1
18th Avenue ADA Ramps

Louisiana Street to Olympia Way

FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $117,224

County: Cowlitz   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 06/30/2025

Project Information

Lead Agency LONGVIEW
Funding Year 2026
Program CSP
Current Phase Audit
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Morgan Palmer
Contact Email morgan.palmer@ci.longview.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 06/30/2025
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 03/22/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/15/2024 03/26/2024
Bid Auth. Approval 10/01/2024 08/30/2024
Construction Approval 11/01/2024 09/26/2024
Project Closeout 05/01/2025 06/27/2025
Audit Date   06/30/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 19,364 9,890
Construction Contract 193,636 184,080
Other Construction 0 0
Total Construction 213,000 193,970
     
Funding Surplus - 95,776  
Total TIB Funding 117,224 193,970

Local Funding Partners

Funding Amount Percent
LONGVIEW 76,746 39.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 76,746 39.6%

Project Description

ADA ramp retrofit adjacent to a city park and a high-volume pedestrian traffic area.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments