Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Poulsbo's Complete Streets Award

C-W-158(001)-1

C-W-158(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $600,000

County: Kitsap   |   Legislative District: 23   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 09/16/2022

Project Information

Lead Agency POULSBO
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 23
Congressional District 6
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Diane Lenius
Contact Email dlenius@cityofpoulsbo.com
TIB Engineer Chris Langhoff
Last Payment Date 09/16/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2022
Delayed Project Date 03/30/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 07/15/2022 08/18/2022
Bid Auth. Approval 07/15/2022 08/18/2022
Construction Approval 07/15/2022 08/18/2022
Project Closeout 04/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 600,000 600,000
Other Construction 0 0
Total Construction 600,000 600,000
     
Total TIB Funding 600,000 600,000

Local Funding Partners

Funding Amount Percent
POULSBO 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
ADA Curb Ramp Upgrades & Installation Pedestrian Mar 2022 $600,000 $ 0
The City has over 700 curb ramps identified in the ADA Transition Plan that are currently non-compliant and more than 50 locations that are missing curb ramps entirely. This project would upgrade 60 to 90 non- compliant curb ramps and install 12 to 20 new ramps within the City limits.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments