TIB Project Information

City of Bellingham's Complete Streets Award

C-W-156(001)-1

C-W-156(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $500,000

County: Whatcom   |   Legislative District: 42   |   Project Length: 0.01   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 07/06/2017

Project Information

Lead Agency BELLINGHAM
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 42
Congressional District 2
Federal Route Number 9999
Project Length 0.01 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Chris Comeau
Contact Email ccomeau@cob.org
TIB Engineer Chris Langhoff
Last Payment Date 07/06/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   02/06/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/06/2017
Bid Auth. Approval 02/15/2017
Construction Approval 02/28/2017 02/28/2017
Project Closeout 12/31/2018 11/13/2018
Audit Date   11/13/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 500,000 500,000
Other Construction 0 0
Total Construction 500,000 500,000
     
Total TIB Funding 500,000 500,000

Local Funding Partners

Funding Amount Percent
BELLINGHAM 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Mahogany Avenue Pedestrian; Bicycle Dec 2016 $500,000 $ 0
New 0.6 mile multimodal arterial street with ADA sidewalks, crosswalks, crossing signals, bike lanes, as well as vehicle travel and turn lanes for vehicles.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.