Projects — TIB Project Information
TIB Project Information
City of Anacortes's Complete Streets Award
C-W-154(001)-1
C-W-154(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Skagit | Legislative District: 40 | Project Length: 0.01 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/06/2017
Project Information
Lead Agency | ANACORTES |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 40 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.01 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Eric Shjarback |
Contact Email | erics@cityofanacortes.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/06/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/06/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/06/2017 | |
Bid Auth. Approval | 02/06/2017 | |
Construction Approval | 02/15/2017 | 02/21/2017 |
Project Closeout | 12/31/2017 | 11/08/2018 |
Audit Date | 11/14/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ANACORTES | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Sidewalk Trip Hazard Repair | Pedestrian | Dec 2016 | $100,000 | $103,000 | |
Anacortes has several blocks of sidewalk in disrepair. We have prioritized the old town area as a focal point. | |||||
ADA Ramp Installation and Retrofit | Pedestrian | Dec 2016 | $100,000 | $100,000 | |
Anancortes has prioritized the old town area as a focal point for ADA ramp installation and repair | |||||
Neighborhood Greenways | Pedestrian; Bicycle | Dec 2016 | $50,000 | $47,000 | |
The Anacortes Bike/Ped plan has several corridors planned for Neighborhood Greenways. This will be a pilot project to create one or two of these greenways. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |