Projects — TIB Project Information
TIB Project Information
City of Port Orchard's Complete Streets Award
C-W-153(001)-1
C-W-153(001)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $650,000
County: Kitsap | Legislative District: 26 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 06/07/2022
Project Information
| Lead Agency | PORT ORCHARD |
| Funding Year | 2023 |
| Program | CSP |
| Current Phase | Audit |
| Legislative District | 26 |
| Congressional District | 6 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Pedestrian |
| Project Contact | Chris Hammer |
| Contact Email | kchammer@cityofportorchard.us |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 06/07/2022 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 03/30/2022 | |
| Delayed Project Date | 03/30/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 05/01/2022 | 05/12/2022 |
| Bid Auth. Approval | 05/01/2022 | 05/12/2022 |
| Construction Approval | 05/01/2022 | 05/12/2022 |
| Project Closeout | 06/30/2025 | 06/25/2025 |
| Audit Date | 06/27/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 650,000 | 650,000 |
| Other Construction | 0 | 0 |
| Total Construction | 650,000 | 650,000 |
| Total TIB Funding | 650,000 | 650,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PORT ORCHARD | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
| Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
|---|---|---|---|---|---|
| Pottery Road Non-Motorized | Pedestrian; Bicycle | Mar 2022 | $650,000 | $650,000 | |
| Add street lighting at high priority locations including school mid-block crossing and intersection with serious injury accident history. | |||||
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||