Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Bremerton's Complete Streets Award

C-W-152(001)-1

C-W-152(001)-1
Complete Streets Award

March 2019 Selection

FY 2020 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $350,000

County: Kitsap   |   Legislative District: 26   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 07/08/2019

Project Information

Lead Agency BREMERTON
Funding Year 2020
Program CSP
Current Phase Audit
Legislative District 26
Congressional District 6
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work Pedestrian
Project Contact Katie Ketterer
Contact Email katie.ketterer@ci.bremerton.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 07/08/2019
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2019
Delayed Project Date 07/01/2021  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2019
Bid Auth. Approval 05/01/2019
Construction Approval 05/01/2019 06/26/2019
Project Closeout 12/31/2022 01/13/2023
Audit Date   01/13/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 350,000 350,000
Other Construction 0 0
Total Construction 350,000 350,000
     
Total TIB Funding 350,000 350,000

Local Funding Partners

Funding Amount Percent
BREMERTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Quincy Square on 4th Street; aesthetic improvements Bicycle Mar 2019 $150,000 $ 0
Bicycle route signage, bicycle parking, and street furniture for Quincy Square on 4th Street. Pacific Avenue to Washington Avenue
Downtown Bremerton Bicycle/Pedestrian Circulation
Improvements
Pedestrian; Bicycle Mar 2019 $350,000 $350,000
Design and install bicycle lane improvements on Washington Avenue from Ferry Terminal to 6th Street. Design and install pedestrian lighting improvements to three pedestrian crosswalks at 2nd and Pacific (2 crosswalks) and 1st and Pacific (1 crosswalk). Design and install an east bound bike lane on Burwell Street from Washington Avenue to Pacific Avenue. Design and install bicycle lane improvements to Pacific Avenue from Burwell Street to the Ferry Terminal.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments