TIB Project Information
City of Port Townsend's Complete Streets Award
C-W-151(001)-1
C-W-151(001)-1
Complete Streets Award
Jan 2017 Selection
FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000
County: Jefferson | Legislative District: 24 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/06/2017
Project Information
Lead Agency | PORT TOWNSEND |
Funding Year | 2018 |
Program | CSP |
Current Phase | Audit |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | David L. Peterson, P.E. |
Contact Email | dpeterson@cityofpt.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/06/2017 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 02/07/2017 | |
Delayed Project Date | 07/01/2019 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/07/2017 | |
Bid Auth. Approval | 02/15/2017 | |
Construction Approval | 02/15/2017 | 04/03/2017 |
Project Closeout | 01/31/2020 | 01/24/2020 |
Audit Date | 02/04/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PORT TOWNSEND | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
Downtown Curb Ramps | Pedestrian | Dec 2016 | $80,000 | $37,574 | |
Install ADA curb ramps downtown on Washington St. between Adams and Madison St and on Monroe St. at Jefferson. | |||||
Uptown Curb Ramps | Pedestrian | Dec 2016 | $30,000 | $40,900 | |
Install ADA curb ramps on Harrison St. at the Post Office or on Lawrence St. | |||||
9th St. Sidewalk Infill | Pedestrian | Dec 2016 | $140,000 | $171,526 | |
Construct 800 fet of sidewalk on 9th st. between Hancock and Grant in the hospital district. |
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |