 Projects — TIB Project Information

TIB Project Information

City of Sedro Woolley's Complete Streets Award

C-W-126(002)-1

C-W-126(002)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $500,000

County: Skagit   |   Legislative District: 39   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 06/07/2022

Project Information

Lead Agency SEDRO WOOLLEY
Funding Year 2023
Program CSP
Current Phase Audit
Legislative District 39
Congressional District 2
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact David Lee
Contact Email dlee@sedro-woolley.gov
TIB Engineer Chris Langhoff
Last Payment Date 06/07/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2022
Delayed Project Date 03/30/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 04/18/2022
Bid Auth. Approval 05/01/2022 04/18/2022
Construction Approval 05/01/2022 04/18/2022
Project Closeout 12/31/2024 11/20/2024
Audit Date   11/20/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 500,000 500,000
Other Construction 0 0
Total Construction 500,000 500,000
     
Total TIB Funding 500,000 500,000

Local Funding Partners

Funding Amount Percent
SEDRO WOOLLEY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Signalized Pedestrian Crossing Pedestrian Mar 2022 $45,000 $96,121
Install a pedestrian crossing of Cook Road just east of the Prospect Road intersection to serve the Janicki Ballfield complex and playground. The crossing would be signalized using RRFBs.
New Sidewalk - State Street Pedestrian Mar 2022 $225,000 $121,797
Install a sidewalk on the north side of State Street between Central Ave and the existing sidewalk in front of the Senior Center (320 LF, 5' wide with planter strip). Project woould also include 4 curb ramp installations.
Replace Sidewalk - Nelson Street Pedestrian Mar 2022 $126,000 $109,203
Replace damaged sidewalk on the south side of Nelson Street between 6th & 7th Streets in the vicinity of elementary school ( 435 LF, 5' wide, separated from roadway). Work also included curb ramp installations.
ADA Curb Ramps Pedestrian Mar 2022 $79,000 $169,315
Install or upgrade ADA curb ramps to eliminate barriers at various locations indentified in the City ADA Transition Plan. Per the ADA Transition Plan, a cost of $15,000 per ramp will be used. This cost includes deisgn, necessary demolition and new construction.
RRFB Installations Pedestrian Apr 2024 $25,000 $17,059
Install RRFB signals at the walking trail crossing on Township Street and at the crossing on the south leg of the Township Street-Ferry

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments