Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Thurston County's Complete Streets Award

C-W-034(001)-1

C-W-034(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $600,000

County: Thurston   |   Legislative District: 22   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 08/15/2022

Project Information

Lead Agency THURSTON COUNTY
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 22
Congressional District 10
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Scott Lindblom
Contact Email Scott.Lindblom@co.thurston.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 08/15/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2022
Delayed Project Date 03/30/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 08/02/2022
Bid Auth. Approval 05/01/2022 08/02/2022
Construction Approval 05/01/2022 08/02/2022
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 600,000 600,000
Other Construction 0 0
Total Construction 600,000 600,000
     
Total TIB Funding 600,000 600,000

Local Funding Partners

Funding Amount Percent
THURSTON COUNTY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Crossing Improvements at Yelm and Chambers/Landview/Donnelly Pedestrian; Bicycle Mar 2022 $500,000 $ 0
Locations recommended from Pacific Ave - Yelm Hwy Midblock Crossing Study completed in 2018. Crossing improvements include installation of sidewalk, curb returns, street lights, markings, refuge islands, flashing beacons and other bicycle and pedestrian safety improvements.
Martin Way & Hensley St Intersection - ADA Improvements Pedestrian Mar 2022 $100,000 $ 0
ADA improvements including sidewalk and ramp replacement.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments