Projects — TIB Project Information
TIB Project Information
Clark County's Complete Streets Award
C-W-006(001)-1
C-W-006(001)-1
Complete Streets Award
March 2022 Selection
FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $750,000
County: Clark | Legislative District: 17 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/05/2022
Project Information
Lead Agency | CLARK COUNTY |
Funding Year | 2023 |
Program | CSP |
Current Phase | Construction |
Legislative District | 17 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | John McSherry |
Contact Email | john.mcsherry@clark.wa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/05/2022 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/29/2022 | |
Delayed Project Date | 03/29/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/01/2022 | 06/16/2022 |
Bid Auth. Approval | 05/01/2022 | 06/16/2022 |
Construction Approval | 05/01/2022 | 06/16/2022 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 750,000 | 750,000 |
Other Construction | 0 | 0 |
Total Construction | 750,000 | 750,000 |
Total TIB Funding | 750,000 | 750,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CLARK COUNTY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Complete Streets Workplan
Item | Type of Work | Date Added | Est. Cost | Actual Cost | Complete |
---|---|---|---|---|---|
NE 130th Avenue Complete Streets Improvements (NE 76th Street-Padden Pwy Trail) |
Pedestrian; Bicycle | Mar 2022 | $500,000 | $ 0 | |
Installing marked crossing with lighting and a RRFB at intersection of NE 130th Avenue and the Padden Parkway multi-use trail; upgrading the school crossing at Hertiage High School including a RRFB and relocating new school flashers; rebuilding noncompliant curb ramps and APS push buttons to meet ADA requirements; upgrading bike markings, pedestrian, school zone and tranisit signage on the NE 130th Avenue corridor and NE 76th street intersection. | |||||
Pedestrian Ramp Reconstruction Various Locations in Salmon Creek and East Clark County |
Pedestrian | Mar 2022 | $250,000 | $ 0 | |
This project will construct or rebuild noncompliant sidewalk curb ramps to meet current Americans with Disabilities Act (ADA) regulations at various locations in Clark County. |
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |