Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Clark County's Complete Streets Award

C-W-006(001)-1

C-W-006(001)-1
Complete Streets Award

March 2022 Selection

FY 2023 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $750,000

County: Clark   |   Legislative District: 17   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 07/05/2022

Project Information

Lead Agency CLARK COUNTY
Funding Year 2023
Program CSP
Current Phase Construction
Legislative District 17
Congressional District 3
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact John McSherry
Contact Email john.mcsherry@clark.wa.gov
TIB Engineer Chris Langhoff
Last Payment Date 07/05/2022
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/29/2022
Delayed Project Date 03/29/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2022 06/16/2022
Bid Auth. Approval 05/01/2022 06/16/2022
Construction Approval 05/01/2022 06/16/2022
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 750,000 750,000
Other Construction 0 0
Total Construction 750,000 750,000
     
Total TIB Funding 750,000 750,000

Local Funding Partners

Funding Amount Percent
CLARK COUNTY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
NE 130th Avenue Complete Streets Improvements (NE
76th Street-Padden Pwy Trail)
Pedestrian; Bicycle Mar 2022 $500,000 $ 0
Installing marked crossing with lighting and a RRFB at intersection of NE 130th Avenue and the Padden Parkway multi-use trail; upgrading the school crossing at Hertiage High School including a RRFB and relocating new school flashers; rebuilding noncompliant curb ramps and APS push buttons to meet ADA requirements; upgrading bike markings, pedestrian, school zone and tranisit signage on the NE 130th Avenue corridor and NE 76th street intersection.
Pedestrian Ramp Reconstruction Various Locations in
Salmon Creek and East Clark County
Pedestrian Mar 2022 $250,000 $ 0
This project will construct or rebuild noncompliant sidewalk curb ramps to meet current Americans with Disabilities Act (ADA) regulations at various locations in Clark County.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments