Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Snoqualmie's Complete Streets Award

C-P-806(001)-1

C-P-806(001)-1
Complete Streets Award

Jan 2017 Selection

FY 2018 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $250,000

County: King   |   Legislative District: 5   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 07/06/2017

Project Information

Lead Agency SNOQUALMIE
Funding Year 2018
Program CSP
Current Phase Audit
Legislative District 5
Congressional District 8
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Collector
Type of Work Pedestrian
Project Contact Brian Coleman
Contact Email Bcoleman@ci.snoqualmie.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 07/06/2017
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   02/07/2017
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/07/2017
Bid Auth. Approval 02/15/2017
Construction Approval 03/10/2017 03/13/2017
Project Closeout 12/31/2019 01/17/2019
Audit Date   02/04/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 250,000 250,000
Other Construction 0 0
Total Construction 250,000 250,000
     
Total TIB Funding 250,000 250,000

Local Funding Partners

Funding Amount Percent
SNOQUALMIE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
Ped Activated RRFB Pedestrian Dec 2016 $62,000 $ 0
Add two dual-facing Rectangular Rapid Flashing Beacons(RRFB) at King Street and SR 202
Pedestrian Fencing Pedestrian Dec 2016 $70,000 $50,238
Intall 1,100 lf of four foot tall fencing adjacent to the active rail line between SE King Street and SE Northern Street
Extend Sidewalk Pedestrian Dec 2016 $50,000 $ 0
Adds sidewalk adjacent to the school on the south side of Newton Street between Doone Avenue and Reinig Place SE.
Install Sidewalk Aug 2018 $40,000 $38,942
Install 300 ft of 8 foot wide sidewalk from the north end of the Railroad Avenue Bridge along SR 202 to the Tokul Roundabout pedestrian crossing.
Sidewalk Repair and Replacement Sep 2019 $140,000 $160,820
Reapair and replace various sections of sidewalks which have been damaged by tree roots or poor foundations and are considered hazardous to pedestrians.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.